Which is not listed as a major method for determining percentage of completion?

Prepare for the Certified Construction Industry Financial Professional Exam. Enhance your career with detailed financial knowledge specific to the construction industry. Utilize flashcards and multiple-choice questions to boost your understanding and readiness!

Multiple Choice

Which is not listed as a major method for determining percentage of completion?

Explanation:
The concept here is how to gauge progress on long-term contracts in order to recognize revenue fairly. The reliable ways to measure how much of a contract is complete are objective progress indicators: cost-to-cost (costs incurred to date divided by total estimated costs), units of work performed (units completed divided by total units), and the physical completion method (the actual physical progress of the work). Efforts expended—tracking how many hours or amount of labor has been spent—is not a major method because hours don’t always align with how much of the contract is actually finished. People can spend a lot of time on rework, idle labor, or activities that don’t translate into completed work, which can distort progress if used as the sole measure. Therefore, the efforts expended approach isn’t considered a standard method for determining percentage of completion.

The concept here is how to gauge progress on long-term contracts in order to recognize revenue fairly. The reliable ways to measure how much of a contract is complete are objective progress indicators: cost-to-cost (costs incurred to date divided by total estimated costs), units of work performed (units completed divided by total units), and the physical completion method (the actual physical progress of the work).

Efforts expended—tracking how many hours or amount of labor has been spent—is not a major method because hours don’t always align with how much of the contract is actually finished. People can spend a lot of time on rework, idle labor, or activities that don’t translate into completed work, which can distort progress if used as the sole measure. Therefore, the efforts expended approach isn’t considered a standard method for determining percentage of completion.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy